Church Street-Montevallo Road Intersection
The Church Street-Montevallo Road Intersection becomes congested during morning and evening rush hours.
The city of Mountain Brook paving project is going well so far, said public works director Ronnie Vaughn.
Paving work on Euclid Avenue is set to be complete on Monday, April 18. The city will also begin deep milling on Montevallo Road near Green Briar Lane Monday after 8:30 a.m.
The work on Montevallo Road will include a pilot truck and an alternate traffic direction in one lane, so there may be short delays.
The city contracted with Dunn Construction Company to resurface streets, and work began on Monday, March 28.
If you have any questions concerning the paving, contact Jackie McClendon at 802-3875.
The roads set to be paved this year include:
- Memory Court - All
- Mountain Avenue - All
- Elm Street - North of Euclid Avenue
- Main Street - North of Euclid
- Cherry Street - North of Euclid
- Peachtree Road - All
- Peachtree Circle - All
- Ross Drive - All
- Forest Avenue - All
- Fairmont Drive - All
- Lorena Lane - All
- Braddock Avenue - All
- Heritage Circle - All
- Azalea Road - All
- Montgomery Drive - All in city
- Bentley Drive - All
- Camelia Drive - All
- Sims Avenue - Between Camelia and Beech
- Nash Circle - All
- Beech Street All in city
- Beech Court - All
- Beech Circle - All in city
- Beech Lane - All in city
- Fox Hall - All
- Green Briar Circle - All
- Haygood Street - All in city
- Sims Avenue - Hagood to Montevallo
- Eastis Road - All
- Green Briar Lane - Euclid to Montevallo
- Norman Drive - All
- Winthrop Avenue - All
- Alden Lane - All
- Clarendon Road - All
- Montevallo Road - From Montcrest to Green Briar
- Old Leeds Road - From Forest Glen to 4100 Old Leeds (Cherokee Rd.)